Parramatta Light Rail 2 enabling works continue along the River Walk/Louise Sauvage Pathway and adjacent to Hill Road and Wentworth Point. Works currently being undertaken during July are outlined below:

  • Construction of temporary access road, staging area and working platform
  • Installation of site compounds, site fencing, hoarding and worker amenities facility
  • General earthworks and excavations
  • Delivery of materials and stockpiling
  • Utility potholing and investigation works within roadways and verges
  • Installation of survey control points, monthly drone survey and relocation of existing marks
  • Installation and connection of temporary electrical, stormwater drainage, sewer and utilities to the construction compound amenities facility
  • Removal of the footbridge at Newington River Walk to enable haul road and rock causeway construction.

Note: temporary closure of Woo-la-ra car park.

Read more here for July construction update from Transport for NSW.